Fwd: [] Draft Agenda Meeting Monday 28 July 2014, 13.00 UTC - CWG on IST
Seun Ojedeji
seun.ojedeji at GMAIL.COM
Sat Jul 26 05:53:30 EEST 2014
sent from Google nexus 4
kindly excuse brevity and typos.
On 26 Jul 2014 11:33, "Milton L Mueller" <mueller at syr.edu> wrote:
>*
> >
> > * ICG timeline is still tentative and will need to be further
> > discussed and considered by ICG - issues such as public comment and
> > consultation has not been factored in
>
> Not true. Public comment has been factored in to the final proposal (see
the draft charter) and consultation should be going on from day one.
>
I think both of you are right by 50% at per; yes there is a mention on how
the consultation will run but there is no clear timeline stated neither is
their clear process to engaging the public (non-component interests). For
instance, I hope you agree that the draft charter is indeed not final and
still in discussion, what's the timeline and channel of communication to
getting a final charter?
> > competing proposals according to charter
> > * Draft timeline does not allow for resolution of possible issues or
> > testing, incl. no transition window
>
> Draft timeline explicitly mentions testing.
>
Maybe not testing for me, but timeline does not explicitly indicate the
need to have phases of public comments. In summary it says:
- proposals received from the 3 components compiled to form single document
- single document published for public comment
- ICG produce final and submits
There is a phase missing between final and submission; ICG should produce
draft2 so it can be observed if it indeed reflects/address the concern of
the wider community.
Regards
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ncsg.is/pipermail/ncsg-discuss/attachments/20140726/a906bbf3/attachment.htm>
More information about the Ncsg-discuss
mailing list